Network Maintenance in Singapore Data Center January 23, 2019

Wednesday, 23 January 3 hours
Complete
Complete

The scheduled maintenance in Singapore is complete. Customers that normally connect to the Singapore data center should direct their ipsec tunnels back to the Singapore data center

Underway

Scheduled maintenance is currently in progress. We will provide updates as necessary.

Scheduled

Network maintenance will occur in our Singapore data center on January 23, 2019, that is expected to last up to 3 hours.

Impact During the maintenance window there will be 2 network outages of up to 10 minutes each.

Required Action IPSec connected customers are requested to bring up their secondary tunnel (if configured) prior to the maintenance

Schedule • Start Date: January 23, 2019 at 17:00 UTC • End Date: January 23, 2019 at 20:00 UTC

Began at: