Network Maintenance in Paris (ORY1) Data Center October 22, 2019

8 hours
Complete
Complete

The scheduled maintenance has been completed.

Underway

Scheduled maintenance is currently in progress. We will provide updates as necessary.

Scheduled

Network maintenance will occur in our Paris (ORY1) data center on October 22, 2019, starting 16:00 UTC, and is expected to last up to 8 hours.

Impact There may be a brief service disruption during the maintenance window.

Required Action IPSec connected customers are requested to bring up their secondary tunnel (if configured) prior to the maintenance.

Schedule • Start Date: October 22, 2019, at 16:00 UTC • End Date: October 23, 2019, at 00:00 UTC

Began at: